GANGAVARAM & VIZAG PORT DEVELOPMENTS
May 20, 2015 5:23 pmPlease find port developments of Gangavaram & Vizag Ports as under :
PORT DEVELOPMENTS.
GANGAVARAM PORT
Gangavaram Port authorities have completed all the arrangements for Berth No-6 for facilitating the vessels to discharge cargo by using of Shore Gantry Cranes through conveyor system. Please be informed that MV.CHANNEL ALLIANCE cape vessel berthing at Berth No-6 on 21.05.2015 under trail basis for discharging 164996 MTS of steam coal on account of M/s. Bhushan Steels.
Berth details are given below:
Permissible LOA – 292 mtrs \ BEAM – 48.00 mtrs / DRAFT – 17.50 mtrs / Displacement 235000 mt.
Please note Berth no 7 & 8 ready for operations and port likely to berth vessels under trail run. Waiting for statutory clearance to commence commercial operations officially.
VIZAG PORT
In today’s Port Berthing Meeting, Port has informed that MV.TAN BINH 22 would be berthing at WQ-6 to discharge Lime Stone Cargo of abt 6100 Mt on trail run basis. Previously only WQ 1 TO WQ 5 Berths was in operation.
WQ-6 berth is operated by M/s. West Quay Multiport Pvt Ltd (WQMPL) A JOINT VENTURE OF ABG Infra Logistics Ltd., and ABG-LDA (Louis Dreyfus Armateurs SAS) .
Berth Details are given below:
Permissible LOA – 225 mtrs \ BEAM – 32.25 mtrs / DRAFT – 14.50 mtrs
Technical Specifications – 2 Shore Gantry Cranes of 60 mt each with Hoppers.
As per port, only specific cargoes will be handled at this berth i.e., LAM COKE / PET COKE / GRANITE BLOCKS AND STEEL PRODUCTS